Ximen Progresses on Kenville 257 Portal Installation, One Step Closer Towards Production

VANCOUVER, BC / ACCESSWIRE / July 29, 2020 / Ximen Mining Corp. (TSX.v:XIM) (FRA:1XMA) (OTCQB:XXMMF) (the “Company” or “Ximen”) is pleased to provide the following update on progress at the Kenville Gold Mine project in the Nelson mining camp in southern British Columbia.

Work on the 257 portal is continuing non-stop under the direction of the company’s consultant geotechnical engineer and site manager. The slope above the portal has now been secured with geotechnical bolting to prevent any soil creep. Now the major excavation of gravel around the outside of the portal will start using an excavator and loader. Ximen recently purchased a new Hitachi 190 excavator for this work. Once the excavation is complete, screening will be installed and the bed for the steel culvert will be prepared. Preparation of the rock face and installation of steel and timber sets will be done prior to placement of the portal culvert. After the culvert is installed, the gravel backfill will be placed around the culvert. Finally, mine services (air and water lines) will be installed and connected to the underground workings. After everything that has been mentioned before has been completed the company can finally focus on producing the first Dore Bar.

Photo of new Hitachi 180 for Kenville portal excavation

Proactive Ximen Mining Video: https://youtu.be/C0BAdcN9-es

Kenville Mine: 257 Portal initial excavation

An updated collation of permit documents was submitted to the regulatory authorities to meet requirements for information. Approval of the new underground development program is anticipated once this material has been reviewed.

Photo of completely bolted and secured slope above portal site.

Kenville Mine: steel culvert for new 257 Portal

Dr. Mathew Ball, P.Geo., VP Exploration for Ximen Mining Corp. and a Qualified Person as defined by NI 43-101, approved the technical information contained in this News Release.

On behalf of the Board of Directors,

Christopher R. Anderson

Christopher R. Anderson,
President, CEO and Director
604 488-3900

Investor Relations:
Sophy Cesar,
604-488-3900,
ir@XimenMiningCorp.com

About Ximen Mining Corp.

Ximen Mining Corp. owns 100% interest in three of its precious metal projects located in southern BC. Ximen`s two Gold projects The Amelia Gold Mine and The Brett Epithermal Gold Project. Ximen also owns the Treasure Mountain Silver Project adjacent to the past producing Huldra Silver Mine. Currently, the Treasure Mountain Silver Project is under a option agreement. The option partner is making annual staged cash and stocks payments as well as funding the development of the project. The company has recently acquired control of the Kenville Gold mine near Nelson British Columbia which comes with surface and underground rights, buildings and equipment.

Ximen is a publicly listed company trading on the TSX Venture Exchange under the symbol XIM, in the USA under the symbol XXMMF, and in Frankfurt, Munich, and Berlin Stock Exchanges in Germany under the symbol 1XMA and WKN with the number as A2JBKL.

This press release contains certain “forward-looking statements” within the meaning of Canadian securities This press release contains certain “forward-looking statements” within the meaning of Canadian securities legislation, including statements regarding the receipt of TSX Venture Exchange approval and the exercise of the Option by Ximen. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are statements that are not historical facts; they are generally, but not always, identified by the words “expects,” “plans,” “anticipates,” “believes,” “intends,” “estimates,” “projects,” “aims,” “potential,” “goal,” “objective,” “prospective,” and similar expressions, or that events or conditions “will,” “would,” “may,” “can,” “could” or “should” occur, or are those statements, which, by their nature, refer to future events. The Company cautions that forward-looking statements are based on the beliefs, estimates and opinions of the Company’s management on the date the statements are made and they involve a number of risks and uncertainties. Consequently, there can be no assurances that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Except to the extent required by applicable securities laws and the policies of the TSX Venture Exchange, the Company undertakes no obligation to update these forward-looking statements if management’s beliefs, estimates or opinions, or other factors, should change. Factors that could cause future results to differ materially from those anticipated in these forward-looking statements include the possibility that the TSX Venture Exchange may not accept the proposed transaction in a timely manner, if at all. The reader is urged to refer to the Company’s reports, publicly available through the Canadian Securities Administrators’ System for Electronic Document Analysis and Retrieval (SEDAR) at www.sedar.com for a more complete discussion of such risk factors and their potential effects.

This press release shall not constitute an offer to sell or the solicitation of an offer to buy any securities, nor shall there be any sale of securities in any state in the United States in which such offer, solicitation or sale would be unlawful.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Ximen Mining Corp
888 Dunsmuir Street – Suite 888, Vancouver, B.C., V6C 3K4 Tel: 604-488-3900

SOURCE: Ximen Mining Corp.

View source version on accesswire.com:
https://www.accesswire.com/599415/Ximen-Progresses-on-Kenville-257-Portal-Installation-One-Step-Closer-Towards-Production

error: Content is protected !!